Skip to content
MRK Real Estate

What happens if I miss an off-plan payment in Dubai?

The developer must report the default to the Dubai Land Department, which gives you 30 days' written notice to pay. If you neither pay nor settle, the developer may terminate and keep up to 25% of the unit's value where construction is below 60%, or up to 40% above that. You may still go to court.

Reviewed by MRK Real Estate Brokers, RERA ORN 17024 · Official sources checked on · Updated

What the developer may do at each stage of construction

Article 11 of Law 13 of 2008, as replaced by Law 19 of 2020, ties the developer's options to the project's completion percentage, which the Dubai Land Department certifies. The percentages are of the value of the unit in the sale agreement, not of the amount you have paid.

Developer's options after the 30-day notice expires (Law 19 of 2020, Article 11)
Project completionWhat the developer may doMost it may keep on termination
More than 80%Keep the agreement, retain all amounts paid and claim the balance; or ask the Dubai Land Department to sell the unit at public auction to recover what is owed; or terminate.Up to 40% of the unit's value
60% to 80%Terminate the agreement unilaterally.Up to 40% of the unit's value
Below 60%, construction startedTerminate the agreement unilaterally.Up to 25% of the unit's value
Not started for reasons beyond the developer's control, or project cancelled by the regulatorThe developer must refund all payments made by purchasers.Nothing
After termination, any amount above the permitted retention must be refunded within one year of termination or within 60 days of reselling the unit, whichever is earlier.

The procedure, step by step

  1. The developer notifies the Dubai Land Department of the missed payment on the department's form, describing the unit and the obligation breached.
  2. The Dubai Land Department verifies the breach and serves you a dated, written notice giving 30 days to perform, delivered in person, by registered mail or by email.
  3. Where possible, the department mediates a settlement. An agreed settlement is attached to the sale agreement as an addendum signed by both sides.
  4. If the 30 days pass without payment or settlement, the department issues the developer an official document confirming the procedure was followed and stating the project's completion percentage.
  5. Only then may the developer use the options in the table, without going to court or arbitration.
  6. You keep the right to go to court or arbitration. The law states that these rules are part of public order and that an act that does not follow them is void.

A worked example

AED 2,000,000 unit with AED 600,000 (30%) paid when the buyer defaults
Project completionMost the developer may keepLeast refunded to the buyer
50%AED 500,000 (25% of AED 2,000,000)AED 100,000
70%AED 800,000 (40% of AED 2,000,000)Nothing: the amount paid is below the permitted retention
85%, developer terminatesAED 800,000 (40% of AED 2,000,000)Nothing: the amount paid is below the permitted retention
The law says 'up to'. A developer may agree to keep less, which is why the mediation step is worth using.

Why other sites show a different figure

Older articles say the developer may keep up to 30% of the payments made. That was the 2008 wording of Article 11. Law 19 of 2020 replaced it with percentages of the unit's value, and applies to agreements signed before or after it came into force. Other pages mention travel bans, which appear nowhere in this law.

Related questions

Can the developer cancel my contract without notice?
No. Under Law 19 of 2020 the developer must first notify the Dubai Land Department, which serves the 30-day notice itself. The department's deregistration service also requires that the developer's own warning was received or refused at least a month earlier.
Can the developer add penalties to the amount claimed?
The Dubai Land Department's deregistration conditions state that the developer's warning must not include fines, registration fees, service fees or administrative fees: only the instalments owed on the price of the unit.
Does this apply to contracts signed before 2020?
Yes. Paragraph (d) of the new Article 11 applies the rules to all off-plan sale agreements concluded before or after the law's effective date.

Sources

Official pages opened and read by MRK on the date shown. Fees and rules change; the linked page is the authority.

  1. Supreme Legislation Committee, Dubai Legislation Portal: Law No. (19) of 2020 Amending Law No. (13) of 2008 Regulating the Interim Real Property Register

    Checked on · Page: issued 24 November 2020

  2. Dubai Land Department: Request for termination of initial registration (service page)

    Checked on · Page: site last updated 19 November 2026

  3. Dubai Land Department: Dubai Real Estate Legislation (official English compilation, PDF)

    Checked on · Page: compilation; translations dated 2014

This page is general information, not legal, tax or immigration advice. It reports what the linked official pages stated on the date they were checked. Confirm your own case with the authority concerned or a UAE-licensed adviser before you act.

Related tools, projects and answers

Ask about your own case

The answer above is general. If you are buying, selling or financing a Dubai property and want to know how it applies to you, send the question to MRK Real Estate Brokers (RERA ORN 17024), Business Bay. We reply Mon–Sat, 9AM–7PM (Dubai time).

Prefer a call back? Leave two details.

Your details go only to MRK Real Estate.

Established in Dubai in 2016 — office in Business Bay

Ask an Advisor

Send us your situation and an MRK advisor will answer it directly.